2024 UPDATE
​​Work done in 2024;
- Old wrought Iron gates repaired and repainted
- Concrete ramps taken out to reveal original victorian steps (A metal wheel chair ramp will be available)
- Front wall render repaired and re-pebble dashed
- Pews removed 7x rebuilt into free standing around edges of the chapel (Rest recycled into the build)
- Floor dropped by 3"inches to be level with the tiled isles
- Serious damp and wood worm mended in the floor and boards replaced using pew wood
- Stage front totally rebuilt and vents put in to prevent further damp damage
- PA system and Cat 6 cabling put in/ hifi installed
- Floor sanded and varnished
- Pews taken out of the top area/ control room built/ pew wood reutilised to built floor in upper
- Curved wall design built
- Downstairs of chapel painted white/ upstairs started
- Loft to be insulated with 200mm of insulation
- Finishing balcony conversion/ plasterboarding
- Electrics installed into rooms
- Plumbing put in for a vertical radiator in top room ​
- Frontage dig out
​​- Planting done
- Frontage complete - More planting to do in 2025
- Fire Alarm first fix
- Fire doors hung in upper rooms x6
​​​
January/ February:
- Building scaffold/ false floor into chapel
- Plastering balcony conversion
- Sanding floors in balcony converted rooms/ staining floors
- Second fix electrics and fire alarm install
- Building landings and steps required by building control
- Replacing glazing window panels
- Installing blackout blinds
- Painting chapel interior S​
- Painting chapel's plastered rooms
- Electrics lighting
- Carpeting upstairs
- Scaffold coming down
​
February - Landmark - Chapel signed off
March - June:
Converting hall to build accommodation
​
July - Project Complete - Hall & Chapel signed off
​
June 2025
OFFICIAL OPENING​